Title: Application of Hybrid SWARA–BIM in Reducing Reworks of Building Construction Projects from the Perspective of Time
Authors: Khalesi, Hamidreza
Balali, Amirhossein
Valipour, Alireza
Antuchevičienė, Jurgita
Migilinskas, Darius
Zigmund, Viačeslav
Keywords: rework causes
BIM
SWARA method
time
project success
Issue Date: 2020
Publisher: MDPI
Citation: Khalesi, H.; Balali, A.; Valipour, A.; Antucheviciene, J.; Migilinskas, D.; Zigmund, V. Application of Hybrid SWARA–BIM in Reducing Reworks of Building Construction Projects from the Perspective of Time. Sustainability 2020, 12, 8927.
Series/Report no.: 12;21
Abstract: One of the major issues of the construction industry has been the “reworks” that affect the time, quality, and cost of projects. Therefore, reworks and the ineffective use of site resources and materials will always result in significant losses on projects. The development of information technology has led to the widespread use of Building Information Modelling (BIM) to enhance the delivery of more sustainable building construction projects. The purpose of this study is to combine the Step-wise Weight Assessment Ratio Analysis (SWARA) method and BIM technologies to identify and reduce time delays caused by reworks in construction projects. Firstly, 49 rework causes in residential buildings were identified and ranked. Then, BIM was generated and compared to the initial model. It was observed that working hours were reduced by 4.6%. Moreover, using an Earned Value Management (EVM) system, a 0.06 increase in Schedule Performance Index (SPI) factor was illustrated. Results obtained by this study provide an effective step in reducing a project’s time in the construction industry.
Description: This article belongs to the Special Issue Sustainable Construction Engineering and Management
URI: http://dspace.vgtu.lt/handle/1/4047
ISSN: 2071-1050
Appears in Collections:Moksliniai straipsniai / Research articles

Files in This Item:

File Description SizeFormat
Application of Hybrid SWARA–BIM in Reducing Reworks of Building Construction Projects from the Perspective of Time.pdf19.04 MBAdobe PDFView/Open

Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.

 

Valid XHTML 1.0! DSpace Software Copyright © 2002-2010  Duraspace - Feedback